Our Perth branch recently completed the relocation of a weighbridge for the Shire of Manjimup. The project included the supply of a new foundation to suit the existing weighbridge decks brought across from another site. This required AccuWeigh technicians to attend site and decommission the old weighbridge decks.

2015-08-25-1

Our AccuCivils department constructed a new foundation to the required size and specification. Once the foundation had cured, we worked with the Shire to crane the original decks into the correct positions on new load cells on the new foundation.

After installation, the AccuWeigh team then performed the calibration, commissioning and verification in accordance with Trade Measurement regulations.